Buyer Guide · Eastern Idaho
By Odyssey Homes · October 30, 2026
The short answer
A semi-custom Odyssey Homes new home in Idaho Falls, Ammon and the surrounding Eastern Idaho towns typically takes 6 to 9 months from contract signing to keys. The plan, the season and the weather set where in that range a build lands, and you get a specific timeline at contract. If you need to move sooner, a quick move-in home already under construction cuts that wait.
Six to nine months is the honest range for an Odyssey home, counted from the day you sign the contract to the day you get keys. That is shorter than a from-scratch design, because you start from one of our existing floor plans rather than drawing a new house. The plan is already engineered and priced, so there is no design phase to wait through.
Some items are ordered long before they are installed. Our schedule orders windows 30 working days, about six weeks, ahead of the install date, so the window order moves whenever the install date does.
A quick move-in home is one we have already started on a specific lot with a chosen plan. Buy it earlier and you still pick more of the finishes; buy it later and you move in sooner. We currently have 26 for sale, 6 of them move-in ready.
Every Odyssey buyer gets the Odyssey One client portal, with build updates, photos and decisions in one place. Once the home is past framing and the site is safe, we walk you through it as work progresses.
An Odyssey Homes semi-custom home typically takes 6 to 9 months from contract signing to keys, depending on the plan, the season and the weather. You get a specific timeline at contract.
Buy a quick move-in home that is already under construction. We currently have 26 for sale, 6 of them move-in ready. The earlier in the build you buy, the more finishes you can still choose.
No, but it can slow it. Weather is one of the three things that move a timeline, along with the plan and the time of year the build starts. We account for the season when we give you your timeline at contract.
Late selections and changes after contract are the delays a buyer controls. Long-lead items like windows are ordered weeks ahead of install, so a late window or cabinet decision can push the schedule. Each change after contract is also priced and signed as a change order before the work happens.
Yes. Once the home is past framing and the site is safe, we walk you through it as work progresses. You also get the Odyssey One client portal, with build updates, photos and decisions in one place.
Get Your Real Number
Pick a plan, a lot and your upgrades, and see an itemized total. Or call us at (208) 450-5500.
More buyer guides